4-month pilot proposal for community-owned testing infrastructure and QA capacity

1. Executive Summary

This proposal requests funding for a 4-month pilot of External Test Lab & Community DevNet: a community-owned testing function for Gonka protocol upgrades, DevShards, inference flows, host/broker operations, and geographically distributed network behavior before governance decisions and production rollout.

Item Proposal
Pilot duration 4 months
Requested budget Up to 22,000 USDT per month, plus a one-time 80,000 GNK end-of-pilot recognition payment.
Funding model Monthly tranches: Month 1 prepaid, Months 2–4 released after previous-month deliverables are accepted
Main deliverables Community DevNet, external testing team, public reports, test plans, runbooks and issue tracker
Ownership Community-owned infrastructure and open operational artifacts, with clear handoff plan
Security handling Public-by-default reporting, with private disclosure for security-sensitive findings before remediation

2. Problem Statement

Today, Gonka lacks a dedicated community-owned validation layer for important network changes. The External Test Lab and Community DevNet are proposed to close this gap by providing practical testing capacity, shared infrastructure, and public evidence before releases, governance decisions, or production rollout.

The External Test Lab and Community DevNet will:

  • Validate protocol upgrades, DevShard releases, broker/inference flows, integrations, and other critical network changes before they move forward.

  • Test distributed-network behavior that is hard to verify in local or internal environments, including latency, synchronization, propagation, and regional instability.

  • Use available testing capacity for proactive bug hunting, regression checks, and investigation of known weak points when no release candidate is waiting for validation.

  • Provide a neutral testing path for work delivered by external teams and ecosystem contributors before it is accepted, funded further, or used in production.

  • Help validate vulnerability reports from researchers, audits, or programs such as HackerOne through reproduction, impact assessment, regression testing, and confirmation after remediation.

  • Provide a shared environment where trusted hosts and teams can safely test proposals, integrations, DevShard scenarios, protocol behavior, and early implementation ideas.

  • Produce clearer testing evidence for governance participants, including test plans, dashboards, runbooks, issue trackers, defect reports, security-sensitive disclosure handling, and release-readiness summaries.

This adds a missing validation layer for the Gonka ecosystem while complementing Core Team testing.

3. Roadmap Alignment

This proposal directly implements two projects from the Gonka Network Development Roadmap.

Track 4. Network reliability and observability — Project 2. External testing lab
The roadmap defines an external testing lab for Gonka changes before broad rollout, including changes from Protocol Maintainers, funded external teams, and ecosystem contributors.

This proposal implements that project through the External Testing Team, test plans, smoke and regression checks, defect reports, public issue tracking, and release-readiness reports.

Track 7. Public sandbox and consumer-GPU testnet — Project 1. Public testing sandbox
The roadmap defines a separate test environment for experiments with models, parameters, integrations, DevShard scenarios, protocol-level behavior, validation, settlement, and upgrade testing before mainnet.

This proposal implements that project through Community DevNet: a small, always-on, geographically distributed network for protocol, node, DevShard, operational, integration, and distributed-behavior testing**.**

4. What We Are Building

The project has three connected components.

Component Purpose Main output
Community DevNet Small always-on geographically distributed network for protocol, node, DevShard, and operational testing. 9–13 inference nodes, monitoring dashboard, deployment runbook
Burst GPU Testing Budget Temporary rental of large GPU infrastructure when heavy model or load testing is needed. Monthly rental allowance, test logs, benchmarks, and cost report
External Testing Team Two hands-on QA / infrastructure testing engineers to validate pre-release builds, DevShards, and deliverables from external teams. Test plans, smoke/regression checks, defect reports, readiness reports

5. Community DevNet Infrastructure

  • Target size: 9–13 always-on inference machines plus required network nodes, where feasible within the monthly DevNet infrastructure cap.

  • Topology: part of the DevNet runs as Network Nodes with multiple attached MLNodes, so that realistic multi-MLNode host configurations can be reproduced and tested.

  • Indicative distribution: North America East, North America West, United Kingdom, Germany, France, Finland, and Asian locations depending on network quality and hosting availability.

  • Model profile: DevNet inference nodes are expected to run lightweight instruct models, such as Qwen/Qwen3-0.6B, or equivalent models.

  • Inference nodes: NVIDIA GPU machines with 16 GB VRAM, compatible with the project’s CUDA 13.0 container/runtime stack.

  • Goal: protocol and distributed behavior testing.

  • Monitoring: public dashboard for node availability.

  • Operations: infrastructure lead from the host/DevOps community responsible for provisioning, monitoring, and maintenance.

Public access. The DevNet is intended to serve the broader community, not only the testing team. During the pilot, access for external participants is granted through a lightweight request process — primarily to manage abuse, access control, and node stability while monitoring and onboarding documentation are still being built. Intended external use cases include:

  • hosts rehearsing onboarding and node operations before joining mainnet;

  • developers and users experimenting with inference, smart contracts, and integrations outside the QA team's test plan.

Broader participation is the target state: we intend to move to fully permissionless access as soon as safety, abuse limits, onboarding documentation, and monitoring allow it.

6. Burst GPU Testing Budget

  • Used only when needed for release candidates, large model tests, load tests, and model compatibility checks.

  • Planning assumption: Up to one calendar week (168 hours) of rental per month.

  • For Kimi-class testing, the requirement estimate assumes an ML Node with either 4× NVIDIA B200 or 8× NVIDIA H200, around 640 GB total GPU VRAM, 960 GB+ system RAM, 16-core amd64 CPU, and a Network Node host with 16-core CPU, 64 GB+ RAM, 1 TB NVMe, and at least 100 Mbps networking.

Access and accountability. Burst GPU capacity is provisioned and coordinated by the External Testing Team together with the project owners, primarily for release-candidate validation, model compatibility, and load tests. Requests from Protocol Maintainers and ecosystem teams are accommodated where capacity allows. All burst usage is itemized in the monthly public report: purpose, hours used, and cost per test run, with test logs published alongside.

7. External Testing Team

The proposal funds two external QA / Infrastructure Testing Engineers.

Scope of work

  • Contribute to quality standards and test strategy for the network

  • Define acceptance criteria and test plans for core network lifecycle events and components

  • Build pre-release validation frameworks, including smoke checks and regression coverage for known failure patterns

  • Deploy and verify distributed node and service stacks in production-like environments

  • Validate critical cross-system flows end to end, with documented evidence and clear defect escalation — e.g. participant and key flows, inference and proof-of-compute participation, gateway and proxy behavior

  • Use health signals, chain queries, and logs as primary validation inputs, not just debugging aids

  • Verify upgrade readiness, rollback feasibility, and post-change health across the stack

  • Establish, tune, and document practical operational primitives, such as PoC validation threshold and inference validation threshold settings, based on DevNet experience, and contribute these findings directly to the official Gonka documentation where appropriate.

  • Support DevNet validation and release-readiness assessment before production rollouts

  • Validate recovery and incident resolution through root-cause analysis and re-testing

  • Report defects with clear reproduction steps, impact assessment, and release-blocking status

  • Track and communicate quality metrics that reflect network health and operational reliability

Required capabilities

  • 3+ years in system QA / Test Engineering, SDET, or quality-focused DevOps/SRE

  • Understanding of blockchain lifecycle, key and auth flows: registration, delegated permissions, fee grants

  • Experience in operation and validation of blockchain nodes (Cosmos SDK preferred): sync, recovery, RPC queries, network phase behavior

  • Experience validating distributed systems in production-like environments

  • Strong test design: test plans, acceptance criteria, smoke/regression/e2e, edge cases, negative testing

  • Solid Linux, SSH, shell scripting, and log-based verification

  • Docker & container orchestration - including environment and config reload behavior

  • Clear defect reporting and documentation — runbooks, test results, sign-off checklists

  • Comfort with time-boxed validation before critical network events

Preferred / Nice-to-Have

  • SDET experience: scripted validation, CI pipelines, automated health checks

  • Blockchain / Web3 QA: testnet operations, bridge testing, wallet/key flows, upgrade regression

  • Cross-chain testing: EVM testnet validation, withdrawal flows, contract interaction

  • GPU/ML inference testing: worker health, model serving, artifact delivery

  • Experience with coordinated multi-node upgrades

  • API gateway and proxy testing (failures, latency, request tracing)

  • Decentralized inference or Proof of Compute networks

8. Project Owners and Accountability

Role Proposed owner Responsibilities
Project Lead Sergii Paranko (S∃ga L∈nin) Overall project accountability, governance coordination, scope and milestone control, QA contractor selection and onboarding, public reporting, and testing laboratory oversight.
Infrastructure Lead Mikhail Chudinov (Mitch) DevNet provisioning, hardware selection, regional hosting, monitoring, operational stability, and infrastructure cost control.
External Testing Team 2 hired QA / Infrastructure Testing Engineers Test execution, reports, defect documentation, regression tracking, and release-readiness recommendations.

9. Transparency and Reporting

  • Public dashboard for DevNet health and node status.

  • Public task board for planned, active, and completed testing work.

  • Public issue tracker for non-sensitive bugs, regressions, and operational findings.

  • Monthly public report with deliverables, incidents, spending by budget line, remaining balance, unused funds, and next-month plan.

  • Per-release readiness report before governance vote or production rollout when a release candidate is provided in time.

  • Security-sensitive findings are reported privately to Core Team first; a public placeholder issue is created where appropriate, and details are disclosed after remediation or agreed disclosure window.

10. Protocol Maintainer Coordination

  • The External Test Lab is intended to work in coordination with Protocol Maintainers while remaining an external community testing function.

  • Protocol Maintainers are expected to support initial onboarding by providing technical context, relevant documentation, general guidance, scripts and notes, expected test focus, and clarification of protocol-specific behavior where needed.

  • This coordination helps the testing team become productive faster and reduces the risk of misinterpreting expected network behavior. At the same time, validation reports remain independently prepared by the External Test Lab and are published for the community.

11. Release Validation Handoff Requirements

Validation type Expected handoff
Protocol release / production upgrade Protocol Maintainers provide release candidate, upgrade notes, affected components, and expected test focus at least 7 days before the planned governance vote or production rollout, where feasible.
DevShard / test environment validation DevShards or another testable environment are provided with scope and expected test focus at least 3 days before the expected validation result, where applicable.

Where a governance vote or production rollout is scheduled and testable artifacts are provided in time, the External Test Lab publishes a readiness report covering tested areas, pass/fail results, known risks, and recommendations.

If testable artifacts are provided late or incomplete, the External Test Lab may still perform limited validation, but the report will clearly state the reduced scope, time constraints, and known limitations.

12. Milestones and Acceptance Criteria

Workstream A: DevNet Infrastructure

Milestone Timing Milestone result Public artifacts Payment gate
M1: Setup Month 1 DevNet design agreed, infrastructure procurement started, at least 5 nodes online; infrastructure blockers documented if any. DevNet architecture note; initial status dashboard (live link); draft node deployment runbook. Month 2 funding requires M1 report and acceptance.
M2: Full DevNet operational Month 2 At least 9 nodes online across target regions; monitoring in place. Published node deployment runbook sufficient to reproduce a DevNet node; public dashboard showing all nodes; regional layout summary. Month 3 funding requires M2 report and acceptance.
M3: Stable DevNet operation Month 3 DevNet running stably; operational issues identified and addressed. Updated runbook; incident log for the month; onboarding guide for external DevNet participants, interim infrastructure cost report. Month 4 funding requires M3 report and acceptance.
M4: Pilot completion and reporting Month 4 Pilot infrastructure work concluded; continuation or handoff recommendation prepared. Final infrastructure and cost report; lessons learned; handoff package. No automatic continuation; new vote required.

Workstream B: External Testing Lab

Milestone Timing Milestone result Public artifacts Payment gate
M1: Testing lab setup and QA onboarding Month 1 QA contractors search and selection, onboarding plan, testing lab operating model, initial test strategy. Initial test strategy document; hiring status in the monthly report. Month 2 funding requires M1 report and acceptance.
M2: Testing capability launch Month 2 At least one QA engineer onboarded and executing tests; second onboarded or in final hiring stage. Public task board (live link); public catalogue of test scenarios: smoke checklist and regression checklist; live issue tracker. Month 3 funding requires M2 report and acceptance.
M3: Repeated validation and process stabilization Month 3 Repeatable validation process in place; validation performed where testable inputs were provided. Open repository with initial test automation scripts (smoke-level checks); updated checklists; validation or status reports for the month. Month 4 funding requires M3 report and acceptance.
M4: Pilot completion and reporting Month 4 Validation work concluded; lab processes documented for handoff. Final validation reports; defect summary; lessons learned. No automatic continuation; new vote required.

13. KPIs

KPI Target Verification method
DevNet availability ≥95% monthly availability for stable nodes after full deployment Public dashboard and monthly uptime summary
Release validation coverage 100% of provided release candidates reviewed within the agreed time window, where provided with sufficient lead time and required handoff materials. Public release-readiness reports
DevShard validation coverage 100% of provided DevShard candidates reviewed within the agreed time window, where provided with sufficient lead time and required handoff materials. Public DevShard reports
Public reporting Monthly public report covering deliverables, incidents, spending by budget line, remaining balance, unused funds, and next-month plan. Public document
Issue quality All defects include reproduction steps, expected vs actual behavior, impact, and severity Public issue tracker / private security tracker where needed
Handoff readiness Runbooks and lessons learned documented by end of pilot Published operational documentation

14. Budget Estimate

This is a planning estimate for a 4-month pilot. Unused burst GPU rental budget may roll over within the pilot; any unused funds at the end of the pilot will be returned to the Community Pool.

Budget line Assumption Monthly estimate 4-month estimate Notes
Community DevNet machines * 9–13 inference nodes plus required Network Node services capped at \$5,000/month as a blended planning average. \$20,000 GPU-class node, CPU/RAM/storage/network/region premium included as planning average.
Burst GPU rental ** Up to one calendar week (168 hours) per month of high-end GPU capacity capped at \$6,500/month \$26,000 For H200/B200-class testing, load tests, model compatibility, release candidates.
Operational tooling and reporting services Shared monitoring and operational tools \$250 \$1,000 Domains/DNS, lightweight monitoring, uptime checks, reporting tools, access management, and small cloud services where needed.
External Testing Engineers 2 QA engineers × \$4,000/month \$8,000 \$32,000 Hands-on QA / infrastructure testing, reports, defect tracking.
Subtotal \$19,750 \$79,000
Contingency reserve \$2,250 \$9,000 Used only if needed.
Total requested authorization 22,000 USDT 88,000 USDT Cap for 4-month pilot.

Any unused funds will be returned to the Community Pool at the end of the pilot.

* The cap above raw GPU-hour pricing covers reserved or non-interruptible instances required for always-on operation, regional price premiums outside low-cost US marketplaces, CPU-only Network Node hosts for the multi-MLNode topology, storage and egress, and temporary node duplication during upgrade and failover testing. It is a cap, not a spend target: actual spending will be itemized monthly, and unused funds will be returned to the Community Pool at the end of the pilot.

** Nebius listed B200 on-demand pricing at \$7.15/GPU-hour and H200 on-demand pricing at \$4.50/GPU-hour (June 2026). At these on-demand rates, 4× B200 for 168 hours would cost approximately \$4.8k, while 8× H200 for 168 hours would cost approximately \$6.05k.

15. Payment Schedule

Tranche Amount Timing Condition
Tranche 1 22,000 USDT At pilot start Prepaid to secure machines, tooling, and people for Month 1.
Tranche 2 22,000 USDT After Month 1 report Released after M1 deliverables and public spending report.
Tranche 3 22,000 USDT After Month 2 report Released after M2 deliverables and public spending report.
Tranche 4 22,000 USDT After Month 3 report Released after M3 deliverables and public spending report.
Continuation TBD After Month 4 Requires a new proposal or explicit governance decision.

16. End-of-pilot GNK recognition

The Project Lead and Infrastructure Lead receive no monthly compensation from the pilot budget: all USDT tranches fund infrastructure, tooling, and the External Testing Engineers. Leadership work is recognized only through the one-time GNK allocation below, paid after pilot completion and final report acceptance.

Role Amount Timing Notes
Project Lead 40,000 GNK After pilot completion and final report acceptance Overall project accountability, governance coordination, scope and milestone control, QA contractor selection and onboarding, public reporting, and testing laboratory oversight.
Infrastructure Lead / DevOps operations 40,000 GNK After pilot completion and final report acceptance Provisioning, monitoring, maintenance, region selection, cost control.

17. Open Source, Ownership and Handoff

  • All non-sensitive documentation, test plans, runbooks, dashboards, issue templates, and reports will be public by default.

  • Where code or scripts are created, they will be published under an open-source license compatible with Gonka ecosystem norms unless there is a clear security reason not to.

  • Infrastructure access will not depend on a single individual. The owner model, emergency access process, and handoff procedure will be documented.

  • At the end of the pilot, a community-approved team should be able to take over the DevNet and External Testing Lab using the published runbooks, documentation, and access handoff process.

Decision Requested

Approve a 4-month pilot of External Test Lab & Community DevNet with a maximum budget authorization of 88,000 USDT, paid in four monthly tranches of up to 22,000 USDT each, and 80,000 GNK paid after pilot completion and final report acceptance.


Reports

Monthly Report — Month 1 (2026-07-10 — 2026-08-09) · Open as separate page

Дата публикации: 2026-08-12


Period: 2026-07-10 — 2026-08-09 · Proposal: #82 (discussion) · Next unlock: 2026-08-13

Workstream A — DevNet infrastructure (M1: Setup)

M1 requirement Status
DevNet design agreed Done — architecture note
≥5 nodes online Done — node0–node4 deployed, one provider each, chain gonka-devnet-community; live state on the status site
Infrastructure blockers documented Done — see below

Delivered beyond the M1 bar:

  • Deployment runbook 1.0.0-alpha.1 (net-deployment-runbook/) — reproducible baseline on testnet-0.2.14 (phased CLI: prepare → identities → qualify-ml → genesis → join → verify), governed 0.2.14 → 0.2.15 upgrade rehearsal, single-node stop/start/verify/reset, network reset contract. The M2 artifact "runbook sufficient to reproduce a node" (ROLE-JOIN.md) is already published.
  • Operator handoff flow — an external operator can qualify, deploy, and register a node without receiving coordinator secrets; the coordinator confirms on-chain registration and grants funding/ML permission.
  • Public observability — status site (per-node cards from committed chain state, honest OFFLINE on reset) and Grafana dashboards: 24h network view, 7-day inference view, triage overview.
  • Authenticated access — api.gonka-dev.net/v1: OpenAI-compatible, chain-accounted DevShard v4 gateway (v3/v4 approved via on-chain governance), automatic escrow rotation across epochs, API keys self-issued through a Telegram bot from a finite pool, no artificial per-key quotas.

All images and binaries are pinned by digest; DevNet keys are fully isolated from mainnet.

Blockers encountered (documented and resolved)

  • Blackwell GPU support. The RTX Pro 2000 ML host (compute capability 12.0) is not supported by the MLNode images pinned to the 0.2.14 baseline. Resolved with a pinned hardware-runtime exception: a newer upstream MLNode runtime for that host only, while the chain release and model overlay stay on the baseline (documented in the runbook release profile).
  • PoC validation timing on DAPI 0.2.14. The stock gateway could submit its first MLNode distribution in the same block as a newer store commit, missing the validation snapshot. Resolved with a ten-block PoC validation delay as an explicit test-lab genesis parameter (documented in the runbook).
  • Provider port limitations (Novita.ai). Evaluated as pay-as-you-go GPU capacity: usable for ML hosts, but does not expose the ports a full network node requires. Kept as reserve ML capacity (remaining balance to be attached to a network node's ML host later).

No hard procurement blockers were encountered during Month 1. One recurring friction: some datacenters and GPU neoclouds require KYC before activating servers, which adds delay to provisioning and slows down multi-provider deployment.

Workstream B — Testing lab (M1: Setup and QA onboarding)

M1 requirement Status
Initial test strategy Done — testing/test-strategy.md
QA search and selection Done — first engineer hired and active
Operating model Done — task board, issue templates (defect / validation request / DevNet access), SECURITY.md private disclosure path

Hiring. 60+ CVs screened, 8 candidates interviewed, one QA / infrastructure engineer hired, started on July 28. As part of onboarding he took on the DevNet deployment itself: the runbook, observability, and gateway work above; onboarding continues in Month 2. The search for the second engineer restarts in Month 2, likely with paid listing promotion; one candidate is in the pipeline and receives a test assignment once the DevNet stabilizes.

Incidents

The network spent most of the period in initial deployment and stabilization; instability during bootstrap was expected and was resolved as part of deployment work rather than tracked as incidents. Public monitoring is live (status site with per-node state and validator map, dashboards).

Spending (budget lines per proposal §14)

Line Monthly cap Spent (Month 1) Notes
DevNet machines $5,000 ≈ $1,550 ($1,065 + €420) 5 nodes + dedicated ML host + domain, itemized below
Burst GPU rental $6,500 $100 Novita.ai pay-as-you-go GPU credit (evaluated for ML hosts; balance reserved)
Tooling and reporting $250 $0
External Testing Engineers $8,000 $2,000 first QA engineer salary (paid by Aug 11)
Contingency $2,250 $0
Total $22,000 ≈ $3,650

Infrastructure breakdown (paid invoices; receipts available for review on request):

Date Provider Configuration Role Billing period Amount
07-19 DatabaseMart GPU VPS, RTX Pro 2000 16 GB node4 ML host 1 month $119.00
07-19 OneProvider dedicated CPU (EPYC/64 GB), Portland US node4 network node + public edge 1 month $77.50
07-24 DatabaseMart dedicated, RTX A5000 24 GB node0 (genesis) 1 month $254.77
07-27 OneProvider dedicated + Tesla T4 16 GB, Helsinki FI node1 1 month $331.63
07-27 Novita.ai pay-as-you-go GPU credit burst ML capacity (evaluated; balance reserved) — $100.00
07-28 GIGAGPU dedicated, RTX 3090 24 GB, UK node3 1 month $270.03
07-29 NameSilo gonka-dev.net registration domain 1 year $11.85
07-29 + 08-05 LeaderGPU (LeaderTelecom) dedicated, RTX 4090 24 GB, NL node2 5 weeks €420.00

Month 2 plan (M2 targets)

  • Scale to 9+ MLNodes across target regions; publish the regional layout summary (#3, #4).
  • Publish smoke and regression checklists (#5).
  • Run the second QA engineer hiring round; we aim to close the hire, prioritizing fit over speed (#6).
  • Begin validation work as testable artifacts are handed off (validation requests).